Odisha cabinet approves 600 MW Upper Indravati pumped storage project

Odisha cabinet approves proposal for ₹4,708-crore pumped storage power project

AI summary

The Odisha cabinet approved the 600 MW Upper Indravati Pumped Storage Project at Ranibahal in Kalahandi district, with state spending of INR 4,708.64 crore including INR 3,371.88 crore for construction. Megha Engineering & Infrastructures Ltd (MEIL) was selected as developer, and commissioning is targeted for the 2030-31 financial year. The facility is expected to generate about 1,040 million units of annual peak electricity.

Why it matters

The approval fixes the 600 MW capacity, the INR 4,708.64 crore outlay and a 2030-31 commissioning target, giving equipment suppliers a dated reference for pumped storage demand in Odisha.