Ørsted prepares turbine installation at 2.9 GW Hornsea 3 offshore wind farm

Ørsted Gearing Up for Turbine Installation at 2.9 GW UK Offshore Wind Farm

AI summary

Ørsted is preparing to install turbines at its 2.9 GW Hornsea 3 offshore wind farm in the UK, with the first Siemens Gamesa components at Able Seaton Port and installation vessels mobilising. DEME's Norse Energi has arrived at the port, while Cadeler's Wind Pace is due to mobilise from Hull on 15 November. The project will use 197 SG 14-236 DD turbines, with installation and commissioning running until November 2027.