Grid equipment backlogs grow at GE Vernova, Siemens Energy, ABB and Hitachi
Grid equipment backlogs grow across manufacturers
AI summary
GE Vernova's Electrification backlog reached $42.2 B at the end of September 2026, Siemens Energy reported about $57 B in Grid Technologies backlog, ABB's Electrification backlog reached roughly $16 B and Hitachi's Energy business reported $66.4 B. Hitachi Energy announced about $214 M for a large power transformer factory in Karjan, Gujarat, due in fiscal 2028, while Siemens Energy India plans about $220 M to add 30,000 MVA of large-transformer capacity for 2030–2032.
Why it matters
The backlog figures show how far transformer and grid equipment demand outruns capacity, and the two factory announcements indicate where lead times may ease.