Fengmiao 1 offshore substation energised as foundation work continues
Fengmiao 1 Offshore Substation Energised as Wind Turbine Foundation Installation Continues
The offshore substation at Taiwan's 495 MW Fengmiao 1 wind farm was energised in October after installation was completed, bringing the project's transmission system fully online, developer Copenhagen Offshore Partners said. CDWE installed the 3,400-tonne topside and 8,000-tonne jacket in August, and Jan De Nul pulled in two export cables. The project targets grid connection by the end of 2027.
The milestone ties offshore substation energisation to a 2027 grid-connection target, showing how export cable and topside work sequence on a 495 MW project.
Energising the offshore substation means commissioning tests now shift to the transmission system: verify export-cable insulation resistance and HV withstand, check protection relay settings and trip logic, and confirm transformer and switchgear tests against IEC standards before grid connection. Plan sea-state windows for any remaining offshore measurements, and record baselines for later maintenance.
Written by AI from the report; check test procedures against the standard itself.
Source: offshoreWIND.biz · offshorewind.biz