Skip to content
offshoreWIND.biz· Sara Kosmajac·· 4 days agoAI score34

First monopiles for RWE's 900 MW Nordseecluster B arrive in Eemshaven

First Monopile Batch for Nordseecluster B Arrives in Eemshaven

AI summary

The first ten monopile foundations for RWE's 900 MW Nordseecluster B offshore wind phase have been unloaded at Buss Ports' heavy-lift terminal in Eemshaven, Netherlands. Dajin Heavy Industry manufactured the roughly 81-metre, 1,350-tonne foundations; 60 will be handled at the terminal in 2026 and 2027, with installation due to begin next year. Nordseecluster B is scheduled to enter commercial operation in early 2029.

Source: offshoreWIND.biz · offshorewind.biz