CERC notifies fourth amendment to connectivity and general network access regulations

CERC notifies CERC (Connectivity and General Network Access to the inter-State Transmission System) (Fourth Amendment) Regulations, 2026

AI summary

CERC has notified the CERC (Connectivity and General Network Access to the inter-State Transmission System) (Fourth Amendment) Regulations, 2026. The amendment lets entities withdraw their entire connectivity quantum if final grant is delayed by two years or more, within a 45-day application window, with bank guarantees returned but the application fee forfeited.

Why it matters

The amendment sets concrete timelines and thresholds for connectivity withdrawal, bank guarantee release and storage sizing, giving developers and network planners a clear compliance baseline.