CERC allows 50 MW solar project to keep ISTS charges waiver after delay

Central Regulator Allows ISTS Charges Waiver for 50 MW Solar Project

AI summary

CERC has allowed a 50 MW solar project to retain its eligibility for a 100% waiver of interstate transmission system (ISTS) charges despite missing its commissioning deadline. The project's commissioning was delayed because the transmission system was not available.