Transformers Magazine· Vanja Stimac·· 21 days agoAI score49
Willdan wins engineering and procurement work on 643 MW of substation and BESS projects
Willdan secures work on 643 MW projects
AI summary
Willdan Group has received limited notices to proceed for engineering and procurement on substation and battery storage projects totalling 643 MW, announced on 5 November 2026. The work covers four transformer substations supporting 568 MW of data centre demand and renewable generation in California, Texas and Illinois, plus a 75 MW battery energy storage system in Texas. Contract values, voltage ratings and completion schedules were not disclosed.
Source: Transformers Magazine · transformer-magazine.com