ENTSO-E report sets out Europe's transmission investment needs to 2035
ENTSO-E report sets out Europe’s transmission investment needs to 2035
AI summary
ENTSO-E has published its Transmission Grid Investment and Supply Chain Assessment Report 2026, covering seven asset categories planned by European TSOs from 2026 to 2035. It identifies around 34,000 km of new HVDC cable, 119 new bipolar converter stations against 38 today, 4,238 SF6-free GIS bays, 2,820 new power transformers and over 64,000 km of HTLS conductors.
Why it matters
The asset-by-asset demand figures give manufacturers and procurement teams a ten-year view of where capacity and SF6-free switchgear supply will be needed.