ENGIE reaches financial close on 900 MW Gulf of Suez 3 wind farm in Egypt
ENGIE reaches financial close on 900 MW wind farm in Egypt
AI summary
ENGIE, Orascom Construction and Aeolus have reached financial close on the 900 MW Gulf of Suez 3 wind farm near Ras Shokeir in Egypt. The project will connect to the grid in three phases, with the first 300 MW entering commissioning in January 2028 and full commercial operation scheduled for the third quarter of 2028.
Why it matters
The item sets out the phase dates, ownership split and lenders for a 900 MW wind farm, giving a concrete reference for how large renewable generation is scheduled onto the Egyptian grid.