Adani Energy Solutions wins Bihar transmission project for 2,400 MW Pirpainti plant
The story so far
Adani Energy Solutions Limited (AESL) has secured, through tariff-based competitive bidding, the transmission project to evacuate power from the upcoming 2,400 MW Pirpainti thermal power plant in Bihar. The project is implemented through the special purpose vehicle Vikramshila Power Transmission Limited, which REC Power Development and Consultancy Limited transferred to AESL; AESL signed a share purchase agreement for 100% of the SPV on 21 November 2026. The scope covers 881 circuit km of lines, 3,160 MVA of transformation capacity, four gas insulated substations and 400 kV and 220 kV double-circuit connections, linking 400 kV substations at Jhanjharpur and Begusarai. Commissioning is targeted for the fourth quarter of 2028. Power Line reported expected annual transmission charges of around Rs 5 billion; T&D India said AESL's transmission portfolio will rise to 30,683 circuit km.
Written by AI from the reports · updated 1 day ago
Developments
2 developments
- Nov 23 05:12 · 2 reportsRECPDCL transfers Vikramshila Power Transmission SPV to AdanTransformers Magazine: Adani Energy Solutions acquires 3,160 MVA Bihar transmission project
- Nov 20 06:00 · 2 reportsAESL secures Bihar transmission project for Pirpainti evacuaPower Line: AESL wins Bihar transmission project for 2,400 MW Pirpainti plant
Coverage timeline
Follow the reports to see different sides of the story.
- Transformers MagazineSelectedAdani Energy Solutions acquires 3,160 MVA Bihar transmission project
Adani Energy Solutions signed a share purchase agreement with REC Power Development and Consultancy Limited on 21 November 2026 to acquire Vikramshila Power Transmission Limited, the SPV for a Bihar transmission scheme. The scheme adds 3,160 MVA of transformation capacity and 881 circuit-km of lines, linking the planned 2,400 MW Pirpainti Super Thermal Power Project through 400 kV substations at Jhanjharpur and Begusarai, with delivery scheduled for the final quarter of 2028.
- Power LineSelectedRECPDCL transfers Vikramshila Power Transmission SPV to Adani Energy Solutions
REC Power Development and Consultancy Limited (RECPDCL) has transferred Vikramshila Power Transmission Limited, the SPV for an intra-state transmission project in Bihar, to Adani Energy Solutions Limited, which won the tariff-based competitive bidding process on a build, own, operate and transfer basis. The project evacuates power from the proposed 2,400 MW Pirpainti thermal power plant and links to 400 kV substations at Jhanjharpur and Begusarai.
- T&D IndiaSelectedAdani Energy Solutions wins Bihar transmission project for 2,400 MW Pirpainti plant
Adani Energy Solutions has secured the TBCB-awarded transmission project to evacuate 2,400 MW from the upcoming 3×800 MW Pirpainti thermal plant in Bihar, targeting commissioning in the fourth quarter of 2028. The scope covers 881 circuit km of lines, 3,160 MVA of transformation capacity, four GIS substations and 400 kV and 220 kV double-circuit connections. AESL's transmission portfolio will rise to 30,683 circuit km.
- Power LineSelectedAESL wins Bihar transmission project for 2,400 MW Pirpainti plant
Adani Energy Solutions Limited has secured the transmission project to evacuate power from the upcoming 2,400 MW Pirpainti thermal power plant in Bihar through tariff-based competitive bidding. Implemented by SPV Vikramshila Power Transmission Limited, it covers four gas insulated substations, 400 kV and 220 kV DCDS lines and 881 ckm of lines, with completion scheduled for the fourth quarter of 2028. Annual transmission charges are expected at around Rs 5 billion.
Heat trend
- Current (comparable)
- 5
- Peak (comparable)
- 18Nov 20 15:00
- 24-hour change
- -50%
The trend compares only participants observed continuously, so it may cover less than the current heat. Hover or tap the chart for hourly heat; use the left and right arrow keys to move.