  1. Transformers Magazine58

    Meralco adds 83 MVA transformer at Commonwealth 115/34.5 kV substation

    Meralco has completed an upgrade at its Commonwealth 115/34.5 kV gas-insulated substation in Quezon City, installing an 83 MVA power transformer for the site's second transformer bank. The work also covered 34.5 kV gas-insulated switchgear and associated protection and control equipment. Meralco says the added capacity supports demand from residential, commercial and institutional customers, including the MRT-7 project and nearby government and hospital facilities.

    Why it matters: The item names the transformer rating, voltage levels and GIS scope at a single substation, giving a concrete reference for distribution-capacity upgrades tied to named load growth.

  2. Transformers Magazine69

    Tesla unveils Powercore 9 MVA solid-state medium-voltage platform

    Tesla has introduced Powercore, a solid-state medium-voltage platform that combines transformer, inverter and circuit breaker functions in one enclosure, rated up to 9 MVA / 7.4 MW continuously at 34.5 kV AC with 10 MVA peak for grid-forming operation.

    Why it matters: Tesla's single-stage medium-voltage platform claims 98.86% peak efficiency and a solid-state breaker, giving storage and data-centre planners a concrete alternative to inverter-plus-transformer architecture.

  1. ETEnergyWorld58

    KPIL wins ₹2,610 crore international power transmission order

    Kalpataru Projects International (KPIL) said it received a notification of award for an order worth about ₹2,610 crore in its power transmission and distribution business. The EPC contract covers transmission lines and substations in an international market, and KPIL did not disclose the project location. KPIL said YTD FY27 order inflows exceeded ₹26,000 crore, up over 50 per cent year-on-year.

    Why it matters: The award shows where EPC transmission and substation work is being booked internationally, and the disclosed order inflow gives a scale reference for T&D tender pipelines.

  1. Power Line58

    GE Vernova to acquire Trench Group as Indian suppliers expand capacity

    GE Vernova has signed an agreement to acquire the Trench Group, a high voltage grid equipment supplier, from Triton Partners. In India, TARIL plans Rs 12.5 billion for three plants making bushings up to 800 kV, pressboard and CTCs, while Waaree Transpower has invested about Rs 1.92 billion in a 500 MVA, 400 kV transformer facility due by April 2027.

    Why it matters: The roundup shows Indian transformer and cable capacity being added alongside 765 kV and HVDC line awards, giving suppliers a view of where domestic capacity and demand are moving.

  1. Power Line60

    Advait Energy wins Rs 695.26 million underground cabling order from DGVCL

    Advait Energy Transitions Limited has secured a turnkey order worth Rs 695.26 million from Dakshin Gujarat Vij Company Limited (DGVCL) to convert the 11 kV and 22 kV HT and LT overhead distribution network in Bardoli division, Gujarat, to underground cable.

    Why it matters: The turnkey scope shows what an Indian discom bundles into an 11 kV and 22 kV underground conversion, from GPR surveys to SCADA-ready ring main units and GIS asset tagging.

  1. ENTSO-E78

    ENTSO-E report sets out Europe's transmission investment needs to 2035

    ENTSO-E has published its Transmission Grid Investment and Supply Chain Assessment Report 2026, covering seven asset categories planned by European TSOs from 2026 to 2035. It identifies around 34,000 km of new HVDC cable, 119 new bipolar converter stations against 38 today, 4,238 SF6-free GIS bays, 2,820 new power transformers and over 64,000 km of HTLS conductors.

    Why it matters: The asset-by-asset demand figures give manufacturers and procurement teams a ten-year view of where capacity and SF6-free switchgear supply will be needed.