Power Equipment Daily: Power Equipment News for Friday, November 20, 2026
KVWIRE
Ecuador awards 500 kV interconnection contract with Peru
Corporación Eléctrica del Ecuador (Celec EP) has awarded a contract through its Transelectric unit for a 500 kV interconnection with Peru, covering civil works, equipment, electromechanical assembly, testing and commissioning. The contractor, contract value and construction deadline were not disclosed. The project was estimated at $277.7 M when its environmental licence was updated in September, and the sector plan schedules service in 2029.
Grid Projects
AESL wins Bihar transmission project for 2,400 MW Pirpainti plant
Adani Energy Solutions Limited has secured the transmission project to evacuate power from the upcoming 2,400 MW Pirpainti thermal power plant in Bihar through tariff-based competitive bidding. Implemented by SPV Vikramshila Power Transmission Limited, it covers four gas insulated substations, 400 kV and 220 kV DCDS lines and 881 ckm of lines, with completion scheduled for the fourth quarter of 2028. Annual transmission charges are expected at around Rs 5 billion.
DOE commits $2.8 billion loan to Grid United Wyoming HVDC intertie
The U.S. Department of Energy has issued Grid United a $2.8 billion conditional loan commitment for a 1.8-GW HVDC line in Wyoming linking SPP and WECC. The roughly 106-mile Wyoming Intertie would run from a converter station in Platte County to an existing substation in Carbon County. Grid United expects permitting in 2029, construction in 2030 and operation in 2032 or 2033, depending on HVDC equipment procurement.
NYISO projects New York resource shortfall starting in 2033
NYISO's 2026 Reliability Needs Assessment projects New York's first statewide resource deficiency of about 225 MW beginning in 2033, growing to more than 1,850 MW by 2036, driven by 2,700 MW of new large-load demand. The report cites about 5,400 MW of gas generation unavailable under winter peak conditions and 4,000 MW of aging generation leaving by 2036. NYISO expects to rely on emergency measures about 3.5 days next year, rising to 21 days by 2036.
Scotland approves 1 GW Muir Mhor floating offshore wind farm
The Scottish Government has granted consent for the Muir Mhor floating offshore wind farm, a project of up to 1 GW using 67 turbines located around 63 kilometres off Aberdeenshire. Developer Fred. Olsen Seawind expects it to start generating clean power by 2030, subject to conditions on commercial fisheries and seabird compensation. Scotland now has more than 11 GW of consented offshore wind capacity.
India expands cross-border power links beyond bilateral supply deals
India's cross-border electricity trade is widening from bilateral hydropower and supply arrangements into a broader network of transmission links and market-based trade. In 2025-26 India imported 7,686.87 MUs from Bhutan and 3,340.46 MUs from Nepal, and exported 8,184.26 MUs to Bangladesh. Existing transfer capacity is 1,160 MW with Bangladesh, 7,560 MW with Bhutan and 1,600 MW to Nepal, with more links planned or under construction.
Tenders & Contracts
Waaree Transpower wins ₹1 billion NTPC transformer order for battery storage
Waaree Transpower, a subsidiary of Waaree Energies, has secured an order worth over ₹1 billion (~$10.7 million) from NTPC to supply inverter duty transformers for a battery energy storage project. The transformers will range from 11 MVA to 22 MVA. NTPC has set a target to develop 22 GWh of battery energy storage projects by 2032.
Viviana Power Tech wins ₹124 crore DHBVNL contract for Gurugram feeders
Viviana Power Tech has secured a ₹124 crore turnkey contract from DHBVNL to build 11 kV feeder infrastructure in the Badshahpur subdivision of Gurugram Circle-2. The work falls under the Revamped Distribution Sector Scheme and is to be completed within 15 months of the Letter of Award received on November 18, 2026. The Vadodara-based EPC firm, which builds transmission and distribution infrastructure up to 400 kV, won a ₹466.74 crore turnkey contract from MGVCL in October 2026.
Test Technology
Tesla unveils Powercore 9 MVA solid-state medium-voltage platform
Tesla has introduced Powercore, a solid-state medium-voltage platform that combines transformer, inverter and circuit breaker functions in one enclosure, rated up to 9 MVA / 7.4 MW continuously at 34.5 kV AC with 10 MVA peak for grid-forming operation.
Market & Business
Ofgem opens urgent inquiry into delayed grid connection offers for Phase 1 projects
Ofgem has launched an urgent inquiry into why grid connection offers for many protected and Phase 1 projects have been delayed relative to their pre-reform dates, despite a smaller queue.
NKT's Karlskrona offshore cable factory expansion to start operations in Q2 2027
NKT expects the expanded high-voltage cable factory in Karlskrona, Sweden, to begin commercial operation and ramp up in the second quarter of 2027, slightly ahead of the original schedule, according to its Q1-Q3 2026 interim report. The expansion adds a new factory and a third extrusion tower, 200 metres tall, which NKT says is essential for making longer high-voltage cables. NKT says the site is set to become the world's largest high-voltage offshore cable production site.