CRISIL forecasts India adding up to 274 GW renewables by FY31
A Crisil Intelligence report projects India will add 264 to 274 GW of renewable capacity between FY27 and FY31, plus 50 to 55 GW of energy storage, lifting installed capacity from about 533 GW in FY26 to 835–845 GW by FY31. Hybrid tenders rose from 31.68% of utility auctions in FY21 to 86.94% in FY26, and battery tariffs fell from ₹10.18 to ₹2.1 per unit without viability gap funding. CRISIL estimates ₹37–42 lakh crore of investment, with only 32 GW of ISTS substation margin available as of August 31, 2025.
Standards & Regulation
FERC approves MISO plan to speed legacy interconnection queue studies
FERC on Nov. 20, 2026 approved MISO's plan to clear its legacy interconnection queue, including penalty-free withdrawal before Decision Point II and a single restudy limit in DPP Phase III. MISO said the DPP-2022 cycle, with about 35 GW of active projects, would otherwise have been delayed roughly 18 months. FERC also raised the penalty-free exit threshold from a 35% to a 50% network upgrade cost increase.
Grid Projects
Waaree Energies signs SECI PPA for 700 MW solar-plus-storage project
Waaree Energies has signed a 25-year PPA with SECI for a 700 MW solar project paired with a 700 MW/2,800 MWh battery storage system in Solapur, Maharashtra. The agreement was executed through wholly owned subsidiary Waaree Forever Energies, following SECI's award of the project in August 2026. Tariff and commissioning timelines were not disclosed.
South Korea's 364.8 MW Yeonggwang Nakwol offshore wind farm reaches full output
South Korea's 364.8 MW Yeonggwang Nakwol offshore wind farm began supplying electricity to the grid at full capacity on 18 November 2026, after passing its continuous energisation test and receiving Korea Electrical Safety Corporation certification on 17 November. All 64 Vensys 5.7 MW turbines and the monopile foundations are installed. A 20-year REC agreement with KOSPO sets a fixed combined price of KRW 307.144 per kWh.
New Jersey orders four utilities to launch PowerUp NJ virtual power plant by October 2027
The New Jersey Board of Public Utilities said on Nov. 12 that Atlantic City Electric, Jersey Central Power & Light, Public Service Electric & Gas and Rockland Electric must run interim versions of PowerUp NJ no later than Oct.
Tenders & Contracts
NVVN invites bids for ISTS-connected battery storage with VGF
NTPC Vidyut Vyapar Nigam (NVVN) has invited bids to develop standalone interstate transmission system (ISTS)-connected battery energy storage systems with viability gap funding. The last date to submit bids is December 21, 2026.
Market & Business
Rajasthan High Court quashes retroactive localization rule for BESS projects
The Rajasthan High Court has ruled against Rajasthan Rajya Vidyut Utpadan Nigam (RVUNL) retrospectively imposing a minimum 20% domestic content requirement on developers awarded contracts for 500 MW/2,000 MWh of standalone battery energy storage systems. The decision covers capacity awarded by RVUNL.
Sterling and Wilson Renewable wins over INR 2,050 crore in projects
Sterling and Wilson Renewable Energy said it secured two domestic orders and became the lowest (L1) bidder for a third, with the three projects together exceeding INR 2,050 crore. The orders cover a 600 MWh battery energy storage system turnkey project in Gujarat awarded by a public sector undertaking and a solar project in Rajasthan from a private independent power producer. The company did not disclose individual project values.